Putney Bridge closed for repairs July to October 2014

Posted on Jul 08, 2013

THE REPAIRS TO THE BRIDGE WERE COMPLETED AHEAD OF SCHEDULE AND IT REOPENED ON THE 26TH OF SEPTEMBER

The following information was published previously:

Background:
Repairs to Putney Bridge, which are urgently needed to safeguard the future of this vital river crossing, means it was closed to all vehicle traffic on Monday, July 14. However, the estimated six month closure timetable has been dramatically reduced. Now, engineers are predicting the works could be completed in around half that time.

Council leader Ravi Govindia said: “These works are absolutely vital to protect the internal fabric of the bridge and ensure it lasts another 100 years. “Our primary concern is to get this important job done efficiently and quickly so that there is the least amount of disruption to residents, businesses and the wider travelling public”.
The vast majority of the £1.5m repair programme will be carried out during the school summer holidays when traffic levels are at their lightest. This timetable should also ensure that the bridge will reopen in plenty of time for Christmas so that local businesses can take advantage of the busy festive shopping period.

While the works are ongoing pedestrians will still be able to cross the bridge, as will cyclists, although they will need to dismount. Buses will operate a shuttle service from both ends of the bridge. This means that passengers will need to cross it on foot to carry on their journeys. Motorists will still be able to use other river crossings, while others are expected to switch to public transport. People who make only short journeys north and south of the river may take advantage of the Barclays Cycle Hire Scheme which was extended to Putney and other northern parts of the borough in December 2013.

The timing of the repairs has been drawn up in close consultation with Transport for London, neighbouring highway authorities, local amenity groups, business representatives and other partners to ensure a high level of co-ordination with other major roadworks in south and west London. The programme has also been drawn up to avoid impacting on the Wimbledon tennis championships, while the works have been scheduled so that August’s Ride London cycle event, which attracts thousands of professional and amateur bike riders, can still be accommodated.

The decision to fully close the bridge to all traffic – rather than have a partial closure – was backed by a clear majority of both residents and businesses during the public consultation late last year, although the number of responses to the Council's survey were quite low. The public’s preferred option was getting the job done in the shortest possible time and at the lowest cost to taxpayers.

Cllr Govindia added: “I am pleased that we have dramatically shortened the closure period and ensured that not only will the works be carried out when traffic levels are at their lowest, but that these vital repairs should be completed well before the busy Christmas rush, which is good news for local traders. “Unfortunately a repair job on this scale to an important river crossing means that some degree of disruption is unavoidable, and we are of course very sorry for the inconvenience it will cause, but we have worked very hard to keep this to the absolute minimum. “And we are giving people as much advance warning as we can so that they have plenty of time to plan alternative routes or look at using other forms of transport to get across the river.”

The full letter from the Director of Environmental and Community Services can be read by clicking on this link:- Letter on Putney Bridge Closure

 